Midland Main Line, Kettering to Wigston: energised on programme.

RC Infrastructure delivered overhead line equipment design, install, test and commission across the Kettering to Wigston section of the MML electrification programme.

A newly installed overhead line portal gantry spanning a four-track main line in open countryside, with yellow road-rail machines on the track.
Fig. 6.1A new portal gantry and its wiring across a four-track main line, with plant still on the track.
Value band
£20m+
Duration
Multi-year
Status
Delivered

01Summary

Client, value and status at a glance.

Client
Network Rail (via tier-one alliance)
Capability
Rail
Region
Midlands
Value band
£20m+
Duration
Multi-year
Status
Delivered

02The work

What it took, and how it ended.

  1. The challenge

    A long route, wired around a running railway.

    The Kettering to Wigston section had to be designed, installed and commissioned inside a series of weekend and overnight possessions, with daytime services continuing between them.

  2. What we delivered

    Design, install, test and commission as one package.

    Overhead line equipment design, installation, testing and commissioning across the section, with isolation and possession planning managed by the same team.

  3. Outcome

    Energised on programme.

    The section was energised on programme, with zero unplanned service disruption attributable to our works. Entry-into-service packs cleared audit on first submission.